DESCRIPTION OF WORKS
- All piping works. HDPE, Stainless Steel, Carbon Steel, PE, PP, Corrigated PVC and others.
- Screening Building Equipment
- Oil, Grease and Grit Removal System
- Inlet Pumping Station
- Storage Tank and Blower Station
- Sequencing Batch Reactors (4 Tanks)
- Outlet Flow Measurement
- Excess Sludge Pumping
- Sludge Thickener
- Sludge Dewatering Building
- Coagulant Station
- Control Room
- Exhaust Filter – Odor Control Unit
- Septage Tank
- UV Desinfection Unit
- Washwater and Firefighting System
- Storm Water Drainage Pumping Station
- Setting-Up Laboratory
All electro-mechanical works of the WWTP completed and commissioned by our team successfully.
- Location: Herceg Novi - Montenegro
- Client: Municipality of Herceg Novi
- Contractor: Joint Venture Mass Gintas
- Completion Date: August 2017